The dry walling is finished around the data center area, and painting is almost complete. Today the raised access flooring was delivered. We will begin installing this as soon as the painting is complete. Then the electrical contractor can begin their work and the glass containment for the hot aisle.
The generator exhaust pipe needs to be relocated 20 meters away on the other side of the building, and the air intake vent still needs to be constructed.
Next week the raised access flooring will start to be installed.