Things are progressing in the test data center, in another week or so we have a target date to turn on the system.
Today we are pressure and leak testing the pipes that will carry the chilled and return water from the cooling systems, and continuing the installation of the insulation for the cold water pipes, as well as the electrical distribution boxes for each rack.
Next week we hope to start the installation of the hot aisle containment around the racks and move the AHU’s into place.